Steps
-
Submitting an application for the EIA certificate by filling in a Preliminary Environmental Assessment Registration Form, Please use Registered Environmental Experts when filling in registration form and during preparation of the project
-
Return to NEMC three copies of a duly filled Application Form attached with 10 copies of the Project Brief for screening
-
Contract an Environmental Expert/EIA Consultant to prepare a Scoping Report and Terms of Reference (TORs) for conducting the EIA and submit them to NEMC for review and approval before the commencement of the EIA study
-
Conduct EIA study (by the Consultant) according to the approved TOR
-
Submit an Environmental Impact Statement (EIS) also called Environmental Impact Assessment (EIA) Report to NEMC for review by a Cross-sectoral Technical Advisory Committee (TAC)
-
The Consultant will make improvements of the EIS by incorporating all comments and recommendations raised by the TAC
-
The Consultant will submit the improved (final) version of the EIS to NEMC for final scrutiny. NEMC will forward recommendations to the Minister for Environment for final approval
-
Upon signing of the Certificate by the Minister, it will be brought back to NEMC for collection by the Developer
-
The signed EIS Certificate will be attached with the General and Specific conditions that must be adhered to by the Developer
-
- Inputs
- Output
- Cost
-
Duration
-
30 to 45 working days for screening report approval by the Council
-
14 working days for TORs approval by the Council
-
Time taken to carry out EIS depends on the type and complexity of the individual project
-
The Council shall, within 60 days following submission of EIS carry out its review
-
The Minister may approve or disapprove the EIS within 30 days
-
- Officer in charge
- Contacts
- Legal Justification
Conduct EIA study (by the Consultant) according to the approved TOR